Funded by UNIDO, this project was a part of a wider regional project called "Demonstration of Best Available Techniques (BAT) and Best Environmental Practices (BEP) in the Fossil fuel-fired Utilities and Industrial Boilers in response to the Stockholm Convention on POPs". The main goal of this particular project was to gather data in order assess the effectiveness of the implemented BATs and BEPs on the emission of Dioxins, Furans and Mercury in the Suralaya Power Plant in Indonesia.
DEKONTA, as the main contractor, was responsible to send a team of experts to the field in order to
perform several filed measurements collect and send samples to be analysed in our partner’s
laboratory